About project

AR15573729 “CLEANING EMISSIONS INDUSTRIAL INSTALLATIONS on SOLID FUEL”

Applicant and grantee :
JSC Institute of Fuel, Catalysis and Electrochemistry named after D.V. Sokolsky”

Private partner:
JSC ” Kazakhstan – British Technical University”

Implementation period:
26 months (The period of financial support of the project by JSC “FUND OF SCIENCE”)

R&D results: state no. registration of project 0122RKI0101
“Testing a new system of 2-stage purification based on a catalyst at the first stage and reagent purification based on an acid gas absorber at the 2nd stage, to check the efficiency of flue gas purification”.

Tests of a 2-stage purification scheme were carried out when operating on real gases of the waste heat boiler:
Stage 1 (catalytic): afterburning of CO and hydrocarbons;
2nd stage ( reagent ): absorption of SO 2 , CO, C x H y , NO x
Each stage was tested separately and sequentially combined . Purity up to 98% achieved

Scope: Boiler houses, thermal power station on solid fuel.

The proposed Integrated Treatment System is created on the basis of this RNNTD

The project team is staffed taking into account the relevant skills and competencies of each team member: this is education, qualifications, experience in implementing similar projects, skills in general coordination and management of the implementation process, control and monitoring of compliance with technological details – as part of the team, the authors of the technology patent used in the system cleaning. Monitoring the design and manufacture of products.

And the most important thing is the issue of promoting products, monitoring the market, working with potential customers and attracting them, working with existing consumers of products. Already, work has begun on the sale of products. And the first client waiting for the purification system is the Baskuat Boiler House in Taldykorgan .